teknika hba
ingenierie
GRANBY ZOO
AMAZOO AQUATIC PARK

CLIENT
Granby Zoo

LOCATION
Granby

DURATION
1998-1999
PROJECT CHARACTERISTICS
Project completed within the exceptionally short period of 11 months, including design, production of drawings and specifications, calls for tender and construction. The project was completed within budget. Fast track production methods were employed to ensure that the project schedule was met.
SERVICES RENDERED
Project management, drawings and specifications for the infrastructure and for mechanical and electrical services, geotechnical studies and control services and supervision of the work.
PROJECT DESCRIPTION
Construction of an aquatic park: The Amazoo aquatic park covers 12 acres and includes Quebec ’s largest (3,240 m²) wave pool, with a play area for small children, a 450 metre water-injected adventure river and a 929 m² basin for aquatic games.