teknika hba
ingenierie
REBUILDING OF THE PENMAN DAM

CLIENT
City of Saint-Hyacinthe

LOCALISATION
Saint-Hyacinthe

PÉRIODE DE RÉALISATION
1993-1994
PROJECT CHARACTERISTICS
The project was completed in conjunction with the building of a private mini power station at the end of the dam. This specifically required careful coordination of efforts.
SERVICES RENDERED
Description of methods adopted to repair the downstream side of the dam.
Monitoring of the works at the site.
PROJECT DESCRIPTION
The project involved rebuilding the downstream side of the dam, as well as areas of the crest that had been subject to deterioration or delamination. Some areas with washouts underneath the structure also needed to be repaired.