MOUNT MILLER WIND TURBINE PARK
|
CLIENT
Northland Power inc. and 3Ci Énergie Éolienne
LOCATION
Murdochville (Gaspé Region)
DURATION
2004-2005 |
 |
 |
SERVICES RENDERED
Teknika HBA
assumed the responsibility of consultant, representing the client for:
 |
Integration study for the high-tension network, |
 |
Assistance in assuring respect for market technical and economic clauses, |
 |
Verification of technical documents to ensure market compliance, |
 |
Assistance during construction and implementation. |
|
 |
PROJECT DESCRIPTION
54-MW wind energy project, consisting of :
 |
30 windmills, 1.8 MW each, |
 |
1 electrical collector and distribution, 690 V / 34.5 kV, |
 |
1 switching yard, 34.5 / 161 kV. |
|
 |
|
|
|
|
 |
|